Construction Updates for the week of November 21, 2016
Academic Core Buildings: Building 1 (Science): Work will continue with the footing/pit starts. Concrete pour has been rescheduled to 11/22 & 23. Footing Rebar will continue this week. Site...
View ArticleConstruction update for the week of November 28, 2016
The following construction activities are scheduled for the week of November 28, 2016 – Academic Core Buildings: Building 1 (Science): Remaining Footing Rebar will be installed this week. Work will...
View ArticleConstruction Update 12/6/16
Construction Notice Update: The contractor working on the Academic Core project has now completed all drilling operations to facilitate the installation of the drilled pier foundations. The next phase...
View ArticleConstruction update for the week of December 5, 2016
The following construction activities are scheduled for the week of December 5, 2016 – Academic Core Buildings: Building 1 (Science): Remaining Footing Rebar will continue to be installed this week....
View ArticleConstruction Updates for December 2016 to March 2017
Pine Street/ Key D Road Work: Project Timeline: December 19– January 2 (projected completion) IMPACT: Pine Street will be closed from the tennis court access road up to Key D AC Transit bus stop in Key...
View ArticleConstruction updates for the week of December 12, 2016
Academic Core Buildings: Building 1 (Science): Remaining Footing Rebar will continue to be installed this week. Formwork to foundation footings have been stripped. Rat slabs will be poured this week....
View ArticleConstruction Update for the week of December 19, 2016
UPDATE: Construction Taking Place Starting Monday, December 19, 2016 Ohlone College continues to make progress with our construction projects at the Fremont campus. Some of these projects occasionally...
View ArticleConstruction Update for May 17, 2017
CONSTRUCTION NOTICE: Please be informed that PARKING LOT D will be closed for the construction of the next phase of the Geothermal Ground Loop project. The lot will be closed starting Monday, May 22nd,...
View ArticleConstruction Update for May 31, 2017
CONSTRUCTION NOTICE UPDATE: Construction on the Geothermal Ground Loop project will be in progress in the driveway north of Lot D and part of Lot E. This phase will occur starting June 5 through June...
View Article
More Pages to Explore .....